1
visibility
Which two actions should a project manager consider while launching a new virtual team? (Choose two)
-
A
Identify the types and quantities of resources required for each work package or activity
-
B
Verify if team members are on more than one team and cannot devote enough time to this team
-
C
Establish, in the beginning, how progress will be monitored and the best means for communicating progress
-
D
Recruit the best resources within the organization to be part of the virtual team
-
E
Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls.
همان طور که بیان شد دو پاسخ صحیح هستند.