A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors. Which two documents should the project manager update as soon as possible? (Choose two)

  • A

    Change log

  • B

    Issue log

  • C

    Backlog register

  • D

    Risk register

  • E

    Stakeholder register

هم ثبت تغییر و هم ثبت مسائل برای این امر اهمیت دارد.