1
An agile project is in its sixth iteration out of 10. After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product, What two actions should the project manager take? (Choose two)
-
A
Ask the team members to include the change in the next iteration
-
B
Ask the product owner to review the product backlog
-
C
Ask the team members to analyze the impact of this change.
-
D
Ask the sponsor to approve the change request
-
E
Ask the stakeholders about the priority of this change