In a multinational, multi-location project with virtual teams, a project manager has established a project baseline. The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project. What should the project manager calculate to address this critical budgetary situation? (Choose two)
-
A
Currency exchange rate
-
B
Benefits management control in the project
-
C
Contingency control in the project and re-baseline
-
D
Integrated change control in the project
-
E
Mitigation control in the project