The city has decided to build a new train station The project will include various approaches. The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle. Some neighbors are resisting the project, have been asking the mayor to stop the project, and are threatening legal action. What two actions should the project manager take? (Choose two)

  • A

    Discuss with the construction team alternatives on moving the new train station to another location

  • B

    Register this situation as a risk and develop a mitigation plan

  • C

    Have a meeting with the mayor and explain the importance of the new train station to the city

  • D

    Publish information on the city’s website about the benefits that the new train station will bring

  • E

    Conduct regular meetings with the neighbors to get their buy-in for the project.