During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks. How should the project manager address this situation?

  • A

    Call for a team meeting to decide if the changes should be included.

  • B

    Communicate the concerns to the project management office (PMO) during the weekly project reports.

  • C

    Initiate the change request to modify the scope and adjust the timelines.

  • D

    Conduct an impact analysis and present the results to the steering committee for approval