1

As the Developers start work during the Sprint, they realize they have selected two much work to finish in the Sprint. What should they do?

  • A

    Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.

  • B

    Find another Scrum Team to give the excess work to.

  • C

    Inform the Product Owner at the Sprint Review, but prior to the demonstration.

  • D

    As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.