1
visibility

A project manager of a large company needs to categorize the stakeholders’ involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams. Drag each stakeholder scenario on the left to the correct engagement level on the right.

Senior Management
Sales team not aligned to delivery teams
Vendors for the project
Investors who do not fully understand the project implementation scenarios
Supportive
Resistant
Leading
Unaware

پاسخ صحیح به شرح زیر است:

Supportive: Vendors for the project

Unaware: Investors who do not fully understand the project implementation scenarios

Resistant: Sales team not aligned to delivery teams

Leading: Senior Management