1
visibility
A project manager of a large company needs to categorize the stakeholders’ involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams. Drag each stakeholder scenario on the left to the correct engagement level on the right.
Investors who do not fully understand the project implementation scenarios
Sales team not aligned to delivery teams
Vendors for the project
Senior Management
Resistant
Supportive
Leading
Unaware
پاسخ صحیح به شرح زیر است:
Supportive: Vendors for the project
Unaware: Investors who do not fully understand the project implementation scenarios
Resistant: Sales team not aligned to delivery teams
Leading: Senior Management